THIS IS EASY
The Subject Permit:
“Construct a temporary spoil disposal and dewatering system for material removed during the Hernando Beach channel dredging activities.” The dredge material disposal site DMDS or containment dike (bathtub) was to be located on property surrounded on three sides by Minnow Creek and on the fourth by homes. The dredge material, known as slurry; sand, mud, and water, was to be pumped into the containment dike. The maximum permitted fill height for the dike was 5.5 ft. A control pipe, also called a weir, was located with the opening at 6.5 ft, one foot above the maximum fill height to “prevent the overtopping.” The control pipe is an emergency overflow preventer just like in your bathtub. The control pipe was connected to nearby Mullet Canal. see figure A. The only way to discharge water from the containment dike into Mullet Canal is by the emergency control pipe.
Figure A
Th
e Permit verbiage: “A minimum freeboard elevation of 1 ft. from the weir crest elevation of 6.5 ft. shall be maintained at all times for the maximum operating level 5.5 ft. in order to accommodate the 25 year, 24 hour storm and prevent the overtopping of the embankment. The permittee shall ensure that pumping activities temporarily shut down when the slurry approaches the 1 ft. to weir crest elevation freeboard limit. Pumping activities shall not resume until the minimum 1 ft. freeboard from the weir crest elevation is re-established.” Page 17 Hernando Beach DMDS 27-0278629-0019
Hernando County’s response to questions posed by the Petitioners (the county’s opponents in the hearing) and filed with the Department of Administrative Hearings is as follows: “The subject DMDS permit is based upon the discharge of water of acceptable quality from the spoil containment dike into Mullet Canal and not upon direct percolation within the impoundment area.” Repeated: Interrogatories #11, #14, and admission #11
The Hernando County Attorney’s Office prepared for the Administrative Hearing regarding this permit for many months. It is logical and reasonable to assume that they read the permit and the responses to the questions posed by the Petitioners. Comparing the responses with the permit clearly shows a huge problem. One of the main allegations in the Petitioners case against the county’s permit was that the project would not function as it was permitted. Admissions proving the allegation of your opponent in a legal procedure ensure your loss. It is the obligation of an Attorney to advise clients, in this case the Hernando County Commissioners, of the strength of their case. It is therefore reasonable to assume that the County Commissioners knew that the permit was worthless.
Faced with a worthless million dollar contested permit, did our County Commissioners withdraw the permit application and hold those responsible for the pursuit to account? No, they did not. They instead chose to disingenuously pursue the bogus permit themselves, at an additional cost of a million dollars to the taxpayer. And so, two million dollars later, what is left is the sad and glaring realization that the cover up included more then just the Hernando Public Works Department.
